This past week we have finished up most of the drywall and started taping in the kitchen. The window installation is progressing and will be mostly done by the end of this week. The exterior soffit is finished and looks great. The roofing is on order and should be installed in a week or so. The front of the jobsite has been rough graded and we are now digging in the landscape wiring and site lighting. This will be followed by the starting of the front entry concrete work. Also the electricians have pulled the wire for the switchgear and should be able to get it energized this week. The framers have finished framing the final wall of the building and the plumbers have installed their water heaters.
Fine Arts Buildings
At the fine arts this week we have continued the siding, finishing up the windows and Nanawall door. We have installed the radiant tubing in both buildings and should be laying the floor in both buildings in the next week. Also we have set the water heaters in the mechanical room and will be setting the exterior louvers and boiler this coming week. We are proceeding with the front canopies and should be installing them this week as well.
No comments:
Post a Comment