Student Commons
At the student commons this week we installed our first coat of plaster on the building as well as finished installing all of the roof panels. All of the exterior door frames are installed minus one. All of the kitchen equipment is onsite and mostly installed including the hoods and walkin box. The tectum ceiling has begun and will be continuing through next week. We also installed the drop ceilings in both bathrooms. Next week the long awaited Renlita doors show up onsite and will be installed.
Site Work
As soon as the coast was clear we demolished the lower parking lot and curbs. Now that all of the asphalt and curbs are gone we have surveyed the site to proceed next week with further demo and underground utility work. Also next week we will start the underground electrical to the Fine Arts buildings.
Fine Arts
At the fine arts this week we installed the hardwood floor at the music room. Installed the rest of the casework in the ceramics room and finished the grading for the exterior concrete work. The concrete seat bench has been formed up and poured and the rear stairs have been formed up. Next week we will be pouring a lot of the exterior concrete work and stairs as well as finishing up the rest of the interior trim at the music room and the sealing of the concrete floors in the ceramics and digital media rooms.
Tallant Science Center
We have started the 2nd floor of the TSC and have completed most of the demo and abatement work. Once testing is passed we will begin the framing work.
Richardson Hall work commenced this week with plastic protection and shoring installation. Next week we will begin the demolition of the wall.