At the student commons this week we had a monumental accomplishment. The long awaited Renlita Doors showed up and are currently being installed. Also we are working on the ceilings panels and bathroom trim. The finish coat of stucco is ongoing and the PV system is being installed. The backroad is being addressed and we should be finishing that up shortly. The kitchen is finished with their stainless and will finsh their fire system next week. Also next week we will be finishing the doors and kitchen and also starting to prepare the main room for the topping slab.
Fine Arts Buildings
At the fine arts this week we poured half of the walkways and the concrete stairs. We also have done a first coat of paint on the inside of the buildings and started the wood base. Next week we will be continuing the concrete work, wood base and interior wall panels.
Sitework
On the site this week we started the underground utilities and preparing the site for curbs. Also we are installing the new electrical service to the back of New House. Next week we will finish the electrical service, other underground utilities and preparing the rest of the Fine Arts building hardscape.
Tallant Science Center/Richardson Hall
At Tallant we finished demo and finished all of the rough wall framing. Next week we will start installing the new windows and the MEP subs will start their rough-in.
At Richarson Hall we finished the demo of the wall and are now currently sawcutting and excavating for the new footings.