Monday, March 23, 2009

Week of 3/16

Student Commons

At the student commons this week we are over half way done with the roof framing and will continue and finish most of it this coming week. Also we have started and are over halfway done with the mechanical ductwork in the kitchen and bathroom wings. Most of the MEP rough-in is complete and we will be having our inspections this week. Additionally we formed up and poured the back walkway, transformer pad and trash enclosure pad. This coming week we will be finishing up all the loose ends in the wings of the buildings in preparation for insulation and closing the walls as well as erecting the overhang steel for the front of the building.









Fine Arts
At the fine arts we placed the underlayment for the roofing on the Music building and protected the floor so that the electrical and fire sprinkler subs could finish their rough-in. In the ceramics building the MEP's are finishing up in preparation for inspections, while the framer is finishing up their remaining soffit work. We also poured the front footings for the canopies, the kiln floor as well as the mechanical and electrical room floors. Next week we will be finishing up all the loose ends and have our inspections before we insulate the ceilings and walls.


















No comments: