Tuesday, October 28, 2008

Weeks of 10/13, 10/20, 10/27

My apologies for not posting the last couple of weeks. We had an incident out here at our jobsite trailer where a number of things were stolen including my camera and computer which are vital to bring you this blog. We are now back up and running so please look for the weekly postings to continue. Thanks for your patience.

Student Commons

Over the past two plus weeks there has been a lot going on. We have finished up the underslab drainage, plumbing, electrical, fire water, domestic water, and telecom. The footing have been dug, reinforcement has been placed and we are now looking to reinforce the slab-on grade this week. We are looking to pour the Slab-on-Grade on Wednesday November 5th. This will be a very long day for all involved.



Fine Arts Buildings
At the Fine Arts we have finshed the building pads and have dug for the footings. The reinforcement is going in this week and we are planning to pour the footings on October 31st. We also have finished all of the rough grading around the builidngs and are bringing in the new utility services to the building.

1 comment:

lorisa said...

Hey Alex,

Please email me. I would like to ask you a question.

lorisa.elmquist@yahoo.com

Thank you for your time.