There was a lot going on this week at the New Student Commons. We finished up the underslab drainage and most of the underslab plumbing. We also installed our new Grease Interceptor for the new kitchen. We also finished up the front "Landsaver". We have begun layout for the foundation and also starting the final compaction on the new access road off of 71 Fernhill's driveway. Next week we will be starting the digging for the footings and finish the under parking lot work so that we can finish up the back parking lot for paving.
Fine Arts Buildings
At the Fine Arts we have graded the site and have installed the new "Landsaver", as well as the storm drain running away from the Landsaver. We have also finished reframing the roofing at New House that was needed after the demolition of the New House addition. Next week we will be continuing the storm drain system and starting on the under building utilities.