Student Commons

At the Student Commons we have finished the low roof framing and have started all the electrical, plumbing and fire sprinkler work in the two wings of the building. The trusses are coming along we have two installed and by the end of next week we have to have another two or three installed. As soon as we have some dry weather for an extended amount of time we will roof the two lower sections. Next week we will continue with the truss construction and MEP rough-in.





Fine Arts Buildings
At the Ceramics buildins we have finished the plywood and roof framing and are doing final pickup framing work. At the Music building we have finshed all of the perimeter wall framing and have hoisted the two main ridge beams. Next week we will start on the MEP rough-in at the ceramics and finish the roofing and interior wall framing at the music building.