At the student commons this week we continued with the Truss construction as well as doing a lot of pick up framing workin including finishing all the plywood around the exterior of the building. Additionally we continued with our MEP rough-in which includes our plumbing, electrical, fire sprinkler and hydronic piping. This includes work both the north and south wings of the building. Next week we will continue with the truss framing and begin the bridging between the individual trusses. Also we will try to roof the lower roofs if we have dry weather. The MEP's will continue which will include the mechanical ductwork. As soon as there is a little dry weather we hope to grade and pave the back parking lot.
Fine Arts Buildings
At the fine arts buildings this week we continued the rafters and plywood sheathing at the Music room as well as additional pick up framing. We started the underfloor fire sprinkler at the ceramics building. Next week we hope to get the roof onto the ceramics building as well as continue the MEP rough-in. We tarped the cermaics roof to help keep the crawlspace as dry as possible to help the installation next week.