We have finished up the sanitary sewer line outside of the new building and are now doing the main sanitary sewer underneath the building pad. We have finished the first of three "Landsavers", which help with the dispersement of ground water. We also are starting the underslab drainage and electrical work early next week.





At the Fine Arts, we have piped the sanitary sewer and cleared the site. After the demolition of the addition to the New House we have reframed and should reopen the affected classroom early next week.