Tallant Science CenterThe students re-entered the Tallant Science Center this week for all of their scheduled classes. During the week we have mostly been doing a little bit of pickup work here and there including patching the plaster walls at the bathrooms and the TSC. We are also finishing up getting the new mechanical system fully functioning. This will be accomplished by the end of the day Monday.
Student Commons and Fine ArtsThe Student Commons project is moving right along. We have finished 95 percent of the drilling and will wrap that up next Tuesday. We have also finished the new fire water and domestic water lines and done all the necessary tie-ins and inspections. Next week we hope to start getting the building pad finished up to be able to start the sanitary sewer and the rest of the other underground utilties. We have also started to form the new road down from the 71 Fernhill shared driveway.
The Fine Arts Building is slowly coming along. We are currently placing the new sanitary sewer in the ground after hitting a few roadblocks. We will be demolishing the addition to the New House next week. After that is complete we hope to start clearing and grubbing the site to prepare for the rest of the underground utilities.