We are really progressing at the Tallant Science Center now. This past week we waterproofed the floors, leveled a couple of rooms, finished the walls and started the install of the cabinets. Other items we are finishing up are the mechanical system for the building as well as started painting. The new bathrooms are coming along nicely and will be fully tiled by Monday. The windows and exterior doors showed up and have begun to go in. So next week we will be finishing up the cabinets, windows, doors, and flooring.
At the student commons we have finished the building pad and are wrapping up the new storm drain system early next week. Next week we will also be finishing up the new fire water line as well. We did a test Rammed Aggregate Pier(RAP) on Friday which some people might have heard due to it being a loud operation. We will be installing all of these RAP's next week. Most importantly we had the power poles relocated after we finished the underground joint trench.
At the Fine Arts building we have started preliminary layout and grading. We will most likely be demolishing a part of the New Building next week and starting the sanitary sewer.













No comments:
Post a Comment