Wednesday, July 2, 2008

Week of June 30th






Tallant Science Center

Demolition and the beginning stages of MEP rough-in is underway.


Additionally framing and the procurement of casework and windows has also begun.




Student Commons

Work will start next week on the relocation of some PG&E lines running through the jobsite. Rough grading and shoring will begin in the next couple of weeks.





Our jobsite trailer is arriving on 7/7/08 and will be placed onsite.




Fine Arts Building




This building is not scheduled to start for a couple more weeks.
However, please see the picture of the site and the rendering of what it will look like after completion.




4 comments:

aeneas said...

Looks good Alex. Thanks,
Aeneas

aeneas said...

Alex,
This is good start. Talk to you soon and many thanks.

Anonymous said...

Hi Alex. I am the Communications Director at Branson. I'm happy to come upon this blog as I was planning to post updates on our website. I will post a link to this blog for anyone interested in following the progress. What is your role relative to the construction?
Thanks, Mary Bourke

Alex Elmquist said...

Hello Mary,
I am the Assistant Project Manager for the General Contractor(Herrero Contractors, Inc.). I will be onsite throughout the duration of the project. It will be very nice working here with the school and community.