We will have completed most of the Mechanical/Electrical/Plumbing(MEP's) work by the end of the week and are gearing up for starting sheetrock next week. We are close to being fully framed and will complete the balance this week.


Student Commons/Fine Arts
We have broken ground and will be starting the temporary shoring for the student commons near the end of the week. We have also started and will be completing a joint trench for a new PG&E line that was rerouted from the building pad of the student commons. Work on the Fine Arts Building will start in about a week or two.
We have broken ground and will be starting the temporary shoring for the student commons near the end of the week. We have also started and will be completing a joint trench for a new PG&E line that was rerouted from the building pad of the student commons. Work on the Fine Arts Building will start in about a week or two.