Over the past two weeks at the Student Commons we have finished up the Rammed Aggregate Piers/Helical Mini Piles, tied into the exisiting fire line, and connect the storm drain. Once the piers were complete we regraded on top of the building pad and now are ready to start the sanitary sewer, underslab drainage and concrete in the next couple of weeks. Also we have been working on widening the 71 Fernhill Driveway which will be complete within the next week or so.
At the Fine Arts site we have demolished the addition to the New House and have started clearing the site.